Tuesday, March 22, 2011

Engineering updates

The original soil report required making the foundations 800mm deep and founding them into rock. In some spots, the builder has excavated to 1800mm and still not encountered rock. As a result we've had the engineer on site and he's revised some of the foundation engineering to reflect what he's seeing on site.

 